Sunday, April 5, 2015

More Bridge Work 4/4/2015

Bridge construction has started. Just four more of these sections to reach the other side.

Tuesday, March 24, 2015

Bridge Update 3/24/2015

Now have three bridge footings installed. Had a two and a half week delay due to snow. Only three more footings to go and them we start the bridge construction. Weather man calling for snow again tomorrow. More delays.

Saturday, February 14, 2015

First Bridge Started, Feb. 14, 2015

Jim makes final adjustment to the first bridge abutment.

Monday, December 29, 2014

Dec. 29, 2014

Back at dipping ties in wood preservative. We need 750 more for these for the 50 track panels we have to build.  1000 feet of rail is ordered and will be here soon from RMI.

Wednesday, December 10, 2014

Finished M.O.W. Flat Car

Our Flat Car is finished and ready to help built the railroad. I am trying a new truck and coupler supplier which is Live Steamer Parts.  We shall see how good they are!

Monday, September 29, 2014

M.O.W Flat Car Frame

The start of adding cars to our roster. This M.O.W. flat car is needed to help build the railroad. Just needs paint, trucks, couplers and a wood deck.

Wednesday, September 3, 2014

Progress Update 9/1/2014

End of the line for now. We now have 290 feet of track laid. Next project is the bridge install as seen by the big drop off here.