Wednesday, November 30, 2016

End of Work Year Update - 2016

This year we laid 350 feet of track including a siding, most track laid in one year. First switches ever build for the BFSCRR. Our track total is now 810 feet. Here are a few images of the last track laid before the winter sets in. Had to stop track laying at the next bridge. We will be fabricating the bridge this winter.







Monday, September 5, 2016

The New Transfer Lift

The new lift, with some modifications, can now lift the 400 lb. F7 with no problems. We now have 620 feet of track laid. Back to track panel fabrication.

Wednesday, August 3, 2016

More Track Progress

Haven't updated here for awhile. Now that all of Deer Ridge is graded out we are laying more track. We are now at 540 feet of track laid. More to come.